3330 Steiner St
San Francisco permit 202403218311 · Marina
Ti for restaurant to include interior partion , replacing kithcen equipment and associated mep. fire protection under sepearte permit. no exterior/facade work
- Filed
- Mar 21, 2024
- Issued
- May 28, 2024 (2 months after filing)
- Completed
- Sep 27, 2024 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 12 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 21, 2024 | Mar 21, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 21, 2024 | Mar 21, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 22, 2024 | Mar 22, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 22, 2024 | Mar 22, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 26, 2024 | Mar 26, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 11, 2024 | Apr 11, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 11, 2024 | Apr 11, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 11, 2024 | Apr 11, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 11, 2024 | Apr 11, 2024 | Approved |
Public health review Public Health · HEALTH | Apr 16, 2024 | Apr 16, 2024 | Administrative |
Public health food review Public Health · HEALTH-FD | Apr 16, 2024 | Apr 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 28, 2024 | May 28, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $218,000
| Name | Role | License on permit |
|---|---|---|
| Kevin Hugo Zeller Zero Ten Design | Architect | C32204 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026