28 Woodland Av
San Francisco permit 202403228391 · Inner Sunset
Legalize(e)non-permitted lower level living area as addition to 2nd fl unit 28a woodland ave.verify/upgrade as needed(e)wall & ceiling fire rating,wall & floor insulation.replace(e)electric heating with(n)mini-split heat pump,replace(e)windows w/ larger windows for compliant lighting/ventilation & b
- Filed
- Mar 28, 2024
- Issued
- Apr 28, 2025 (13 months after filing)
- Completed
- Nov 21, 2025 (7 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 26 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 20, 2024 | Mar 28, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Mar 22, 2024 | Mar 22, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 25, 2024 | Mar 25, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 25, 2024 | Mar 25, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Apr 1, 2024 | Apr 1, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Apr 1, 2024 | Aug 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 1, 2024 | Apr 30, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 1, 2024 | Apr 24, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 1, 2024 | Apr 10, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 1, 2024 | Apr 16, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 1, 2024 | Mar 5, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Apr 24, 2024 | Apr 24, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 8, 2024 | May 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 29, 2024 | May 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 6, 2024 | Oct 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 6, 2024 | Aug 7, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 6, 2024 | Aug 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 6, 2024 | Aug 7, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 6, 2024 | Aug 8, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2025 | Jan 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 27, 2025 | Jan 27, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 25, 2025 | Feb 27, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 25, 2025 | Feb 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 25, 2025 | Mar 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 25, 2025 | Mar 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 5, 2025 | Apr 28, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $161,364
| Name | Role | License on permit |
|---|---|---|
| Michael Andreas Froehlich Mf Architect | Architect | C24111 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025