2790 Broadway
San Francisco permit 202403228398 · Pacific Heights
Interior remodel @ all levels.work includes(1)replacing(e)elevator,(2)extending main staircase to two lower fls,replacing(e)secondary staircase. excavation of crawl space at first floor for new habitable space.
- Filed
- Apr 29, 2024
- Issued
- Jan 3, 2025 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 26 stops across 5 departments
- Comments issued
- 11 times, by Permit Center, Building Inspection, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 21, 2024 | Mar 29, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 25, 2024 | Mar 25, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Mar 28, 2024 | Mar 28, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 28, 2024 | Mar 28, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 10, 2024 | Apr 18, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 15, 2024 | Apr 15, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 16, 2024 | Apr 16, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 17, 2024 | Apr 17, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Apr 18, 2024 | Apr 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 19, 2024 | Apr 22, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Apr 22, 2024 | Dec 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 22, 2024 | Jun 18, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 22, 2024 | May 16, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 22, 2024 | Apr 30, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 22, 2024 | Dec 23, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Sep 10, 2024 | Sep 10, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 11, 2024 | Sep 23, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 20, 2024 | Nov 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 27, 2024 | Nov 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 2, 2024 | Dec 3, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 13, 2024 | Dec 13, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 16, 2024 | Dec 16, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 18, 2024 | Dec 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 23, 2024 | Jan 3, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 30, 2024 | Dec 31, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 3, 2025 | Jan 3, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $3,100,000
| Name | Role | License on permit |
|---|---|---|
| Andrew Skurman Andrew Skurman Arch. | Architect | C23797 |
| Kris Wallace Johnson Gfds Engineers | Engineer | 4319 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022