99 Grove St
San Francisco permit 202403258507 · Tenderloin
New telescoping seating system to be installed in extg auditorium. no changes to extg bldg mech. elect. or plmg. no changes to extg building fire alarm and sprinklers.
- Filed
- May 10, 2024
- Issued
- Nov 20, 2024 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 26 stops across 5 departments
- Comments issued
- 9 times, by Building Inspection, Permit Center, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 25, 2024 | Mar 25, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 2, 2024 | Apr 2, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 2, 2024 | Apr 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 18, 2024 | Apr 18, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 22, 2024 | Apr 22, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Apr 23, 2024 | May 1, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2024 | May 13, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 26, 2024 | Apr 26, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 29, 2024 | Apr 29, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 30, 2024 | Apr 30, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 6, 2024 | May 10, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | May 10, 2024 | May 10, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 13, 2024 | Jun 10, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 13, 2024 | May 16, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2024 | May 17, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | May 13, 2024 | Nov 12, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jun 10, 2024 | Jul 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 13, 2024 | Jun 13, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 5, 2024 | Jul 5, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 28, 2024 | Aug 28, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 3, 2024 | Oct 3, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 24, 2024 | Oct 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 25, 2024 | Nov 4, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 25, 2024 | Nov 6, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 25, 2024 | Nov 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 12, 2024 | Nov 20, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $24,000
| Name | Role | License on permit |
|---|---|---|
| Christopher Scott Wasney Cody Anderson Wasney Arch. | Architect | C22197 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026