Mayoral ed 13-01/17-02: erect new 6-story bldg. levels 02-06 provides 120 residential sleeping units, group training rooms & therapist offices to support the residential use. level 01 amenities include a full service kitchen, dining, staff lounge, fitness, multipurpose rooms, & outdoor space.
- Filed
- Oct 16, 2024
- Issued
- Feb 14, 2025 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 146 stops across 7 departments
- Comments issued
- 58 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Health
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 24, 2024 | Apr 3, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 26, 2024 | Mar 26, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Apr 1, 2024 | Apr 1, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 2, 2024 | Apr 2, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Sep 14, 2024 | Sep 24, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 18, 2024 | Sep 18, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 27, 2024 | Oct 16, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 4, 2024 | Oct 4, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Oct 16, 2024 | Oct 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 16, 2024 | Oct 16, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 16, 2024 | Oct 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2024 | Oct 30, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 16, 2024 | Oct 29, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 16, 2024 | Oct 23, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Oct 16, 2024 | Nov 5, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2024 | Dec 2, 2024 | Approved |
Public health review Public Health · HEALTH | Oct 16, 2024 | Oct 16, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 16, 2024 | Feb 7, 2025 | Administrative |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 17, 2024 | Dec 2, 2024 | Approved |
Public health review Public Health · HEALTH | Oct 18, 2024 | Oct 18, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Nov 18, 2024 | Nov 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 11, 2024 | Dec 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 16, 2024 | Dec 20, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 6, 2025 | Jan 6, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 10, 2025 | Jan 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 10, 2025 | Jan 22, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 10, 2025 | Feb 6, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Jan 10, 2025 | Jan 16, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 10, 2025 | Jan 22, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 10, 2025 | Jan 16, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jan 10, 2025 | Jan 16, 2025 | Approved |
Public health review Public Health · HEALTH | Jan 10, 2025 | Jan 16, 2025 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Feb 4, 2025 | Feb 4, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Feb 6, 2025 | Feb 7, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 7, 2025 | Feb 14, 2025 | Administrative |
Addendum 1: Excavation, grading, civil, foundation, & concrete podium, below grade utilities, structural , lands
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 10, 2025 | Mar 24, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 12, 2025 | Jun 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 27, 2025 | Jun 27, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 27, 2025 | Oct 28, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Jun 27, 2025 | Aug 14, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 27, 2025 | Aug 14, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jun 27, 2025 | Jul 9, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 27, 2025 | Jul 7, 2025 | Issued Comments |
Public Health HEALTH-MH | Jun 27, 2025 | Jul 7, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 27, 2025 | Oct 14, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Oct 27, 2025 | Nov 7, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 27, 2025 | Nov 7, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Oct 27, 2025 | Nov 13, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 27, 2025 | Nov 3, 2025 | Issued Comments |
Public Health HEALTH-MH | Oct 27, 2025 | Oct 28, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 25, 2025 | Nov 25, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 2, 2026 | Mar 6, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 2, 2026 | Mar 6, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Mar 2, 2026 | Mar 19, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 2, 2026 | Mar 4, 2026 | Issued Comments |
Public Health HEALTH-MH | Mar 2, 2026 | Mar 3, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 6, 2026 | Mar 6, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 18, 2026 | Mar 23, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 18, 2026 | Mar 23, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 18, 2026 | Mar 23, 2026 | Approved-Stipulated |
Public Health HEALTH-MH | Mar 18, 2026 | Mar 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 13, 2026 | Jul 14, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 13, 2026 | Jul 14, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jul 13, 2026 | Jul 20, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 13, 2026 | Jul 24, 2026 | Issued Comments |
Public Health HEALTH-MH | Jul 13, 2026 | Jul 16, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 24, 2026 | Aug 25, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 24, 2026 | Aug 25, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 24, 2026 | Aug 27, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 24, 2026 | Sep 8, 2026 | Approved-Stipulated |
Public Health HEALTH-MH | Aug 24, 2026 | Aug 26, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Oct 13, 2026 | Oct 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 14, 2026 | Nov 3, 2026 | Administrative |
Addendum 2: Arch
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 6, 2025 | Jul 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 21, 2025 | Jul 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 21, 2025 | Jul 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 21, 2025 | Sep 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 21, 2025 | Aug 5, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jul 21, 2025 | Aug 11, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 21, 2025 | Jul 23, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jul 21, 2025 | Sep 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2025 | Jul 23, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jul 21, 2025 | Jul 23, 2025 | Approved |
Public Health HEALTH-MH | Jul 21, 2025 | Jul 22, 2025 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Jul 21, 2025 | In progress | In Progress |
Mechanical plan review quality control Building Inspection · MECH-QC | Aug 5, 2025 | Aug 5, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 11, 2025 | Sep 11, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 3, 2025 | Nov 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 3, 2025 | Nov 21, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 3, 2025 | Nov 13, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Nov 3, 2025 | Nov 17, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2025 | Nov 6, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Nov 3, 2025 | Nov 14, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 3, 2025 | Nov 20, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Nov 3, 2025 | Nov 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 16, 2025 | Jan 7, 2026 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Mar 26, 2026 | Mar 26, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 1, 2026 | Apr 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 1, 2026 | Apr 22, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 1, 2026 | Apr 10, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Apr 1, 2026 | Apr 20, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 1, 2026 | Apr 10, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Apr 1, 2026 | May 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 1, 2026 | Apr 2, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Apr 1, 2026 | Apr 2, 2026 | Approved |
Public health food review Public Health · HEALTH-FD | Apr 1, 2026 | Apr 9, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 24, 2026 | Aug 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 24, 2026 | Sep 3, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 24, 2026 | Sep 3, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Aug 24, 2026 | Aug 31, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 24, 2026 | Sep 8, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Aug 24, 2026 | Sep 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 24, 2026 | Aug 31, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Aug 24, 2026 | Aug 31, 2026 | Approved |
Public health food review Public Health · HEALTH-FD | Aug 24, 2026 | Sep 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire Department housing review Fire Department · SFFD-HQ | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 3: Mech, plumbing, electrical system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 27, 2025 | Aug 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 8, 2025 | Aug 8, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 8, 2025 | Aug 21, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 8, 2025 | Aug 12, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Aug 8, 2025 | Aug 26, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 8, 2025 | Aug 11, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 8, 2025 | In progress | — |
Public health food review Public Health · HEALTH-FD | Aug 12, 2025 | Aug 20, 2025 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Aug 19, 2025 | Aug 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 12, 2025 | Nov 24, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 12, 2025 | Nov 14, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Nov 12, 2025 | Nov 19, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2025 | Dec 1, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | Nov 12, 2025 | Nov 14, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 23, 2026 | Apr 1, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 23, 2026 | Mar 31, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Mar 23, 2026 | Mar 26, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 23, 2026 | Apr 13, 2026 | Approved-Stipulated |
Public health food review Public Health · HEALTH-FD | Mar 23, 2026 | Mar 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 24, 2026 | Sep 3, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 24, 2026 | In progress | In Progress |
Fire Department housing review Fire Department · SFFD-HQ | Aug 24, 2026 | Sep 3, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 24, 2026 | Sep 8, 2026 | Approved |
Public health food review Public Health · HEALTH-FD | Aug 24, 2026 | Sep 3, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire Department housing review Fire Department · SFFD-HQ | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $40,000,000
| Name | Role | License on permit |
|---|---|---|
| Jeff Brink Dci Engineers | Engineer | S6142 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025