1400 Van Ness Av
San Francisco permit 202403268608 · Nob Hill
At&t: install new mobility unmanned telecom facility: (12) antennas within (3) faux frp radomes, 3 frp enclosures, 12 rrus, gps (1), (4) surge suppressors, power trunk/fiber/conduit, new steel platform pad on rooftop for equipment, (4) cabinets, new h-frame with ciena hoffman box, 200ac power panel,
- Filed
- Mar 26, 2024
- Issued
- Jun 20, 2024 (3 months after filing)
- Completed
- Apr 24, 2026 (22 months after issuance)
- Review stops
- 15 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 26, 2024 | Mar 26, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 26, 2024 | Mar 26, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 26, 2024 | Mar 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 26, 2024 | Mar 26, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 26, 2024 | Mar 26, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 26, 2024 | Mar 26, 2024 | Approved |
Public health review Public Health · HEALTH | Mar 26, 2024 | Mar 26, 2024 | Approved |
Intake Building Inspection · INTAKE | Apr 29, 2024 | Apr 29, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Apr 29, 2024 | Apr 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 29, 2024 | Apr 29, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2024 | Apr 29, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 29, 2024 | Apr 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 29, 2024 | Apr 29, 2024 | Approved |
Public health review Public Health · HEALTH | May 21, 2024 | May 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 20, 2024 | Jun 20, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Seung Kun Oh | Engineer | S6836 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2025