2929 20th Av
San Francisco permit 202403288801 · Sunset/Parkside
Interior remodel to (e) sfd: 1 bathroom remodel, convert a portion of garage to conditioned space (179 sf). seismic upgrades to ground fl. (note: all work at lvl 2 & exterior under 202403218358)
- Filed
- Apr 4, 2024
- Issued
- Jul 3, 2024 (3 months after filing)
- Completed
- Jun 4, 2025 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 20 stops across 6 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 28, 2024 | Mar 28, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 28, 2024 | Mar 28, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 28, 2024 | Mar 28, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Mar 29, 2024 | Apr 4, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 1, 2024 | Apr 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 1, 2024 | Apr 5, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 4, 2024 | Apr 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 5, 2024 | Jun 3, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 5, 2024 | Apr 18, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 5, 2024 | Apr 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 5, 2024 | Apr 19, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 5, 2024 | Apr 11, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 5, 2024 | Jul 2, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 17, 2024 | Jun 27, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 28, 2024 | Jul 2, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jun 28, 2024 | Jul 1, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 28, 2024 | Jul 1, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2024 | Jul 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 28, 2024 | Jul 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 2, 2024 | Jul 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $75,000
| Name | Role | License on permit |
|---|---|---|
| Jason Park Langkammerer At6 Architecture Design | Architect | C28796 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025