530 Moraga St
San Francisco permit 202403288858 · Inner Sunset
Horizontal expansion of (e) 3/f, with relocation and expansion of (e) bathroom.
- Filed
- Apr 17, 2024
- Issued
- Mar 19, 2025 (11 months after filing)
- Completed
- Jul 22, 2026 (16 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 26 stops across 6 departments
- Comments issued
- 10 times, by Permit Center, Building Inspection, Public Works, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 27, 2024 | Apr 3, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 1, 2024 | Apr 1, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Apr 3, 2024 | Apr 3, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 3, 2024 | Apr 3, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 9, 2024 | Apr 17, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 16, 2024 | Apr 16, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 17, 2024 | Apr 17, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 17, 2024 | Apr 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Apr 18, 2024 | Jun 10, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 18, 2024 | Jun 10, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 18, 2024 | May 2, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 18, 2024 | Apr 23, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 18, 2024 | Apr 26, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 18, 2024 | Mar 5, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Oct 28, 2024 | Nov 8, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 9, 2024 | Dec 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 18, 2024 | Dec 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2024 | Jan 13, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2024 | Jan 23, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Dec 20, 2024 | Jan 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 20, 2024 | Jan 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 24, 2025 | Mar 19, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Jan 28, 2025 | Jan 31, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 28, 2025 | Jan 28, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 28, 2025 | Jan 29, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 5, 2025 | Mar 5, 2025 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| Christopher J Dorman Dorman Assoc | Architect | C28300 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022