127 Skyview Wy
San Francisco permit 202404029151 · Twin Peaks
Hybrid jadu conversion of (e) living space (family room) at 1st floor of a single family dwelling. per gov. section 65852.2 (e) dedicated (e) rear entry. integral bath & laundry @ (e) garage for residence. (single family + jadu)
- Filed
- Sep 3, 2024
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 27 stops across 5 departments
- Comments issued
- 4 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 1, 2024 | Apr 11, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 2, 2024 | Apr 2, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Apr 2, 2024 | Sep 3, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 4, 2024 | Apr 4, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 11, 2024 | Apr 11, 2024 | Approved |
Zoning review Planning · CP-ZOC | Sep 3, 2024 | Sep 18, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 3, 2024 | Oct 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 3, 2024 | Sep 18, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 3, 2024 | Sep 13, 2024 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Sep 3, 2024 | Sep 11, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 3, 2024 | Sep 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 3, 2024 | Sep 6, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 3, 2024 | Jan 3, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 1, 2024 | Oct 1, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 7, 2024 | Oct 31, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 7, 2024 | Oct 18, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 7, 2024 | Oct 8, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 7, 2024 | Oct 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 8, 2024 | Oct 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 8, 2024 | Oct 8, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | Oct 31, 2024 | Oct 31, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 1, 2024 | Jan 2, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 1, 2024 | Nov 4, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 1, 2024 | Nov 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 1, 2024 | Nov 5, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 1, 2024 | Nov 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 3, 2025 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $65,178
| Name | Role | License on permit |
|---|---|---|
| Mark Elliott Bucciarelli Baukunst | Architect | C23159 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022