Hybrid jadu conversion of (e) living space (family room) at 1st floor of a single family dwelling. per gov. section 65852.2 (e) dedicated (e) rear entry. integral bath & laundry @ (e) garage for residence. (single family + jadu)

Timeline
Key dates from the city record.
Filed
Sep 3, 2024
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
27 stops across 5 departments
Comments issued
4 times, by Planning, Building Inspection
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 11, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Apr 2, 2024Not Applicable

Central Permit Bureau

Building Inspection · CPB

Sep 3, 2024Administrative

Mechanical pre-screening

Building Inspection · PRE-MECH

Apr 4, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Apr 11, 2024Approved

Zoning review

Planning · CP-ZOC

Sep 18, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Oct 2, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Sep 18, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Sep 13, 2024Not Applicable

Mechanical and energy plan review

Building Inspection · MECH

Sep 11, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 4, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 6, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jan 3, 2025Administrative

Mechanical and energy plan review

Building Inspection · MECH

Oct 1, 2024Approved

Zoning review

Planning · CP-ZOC

Oct 31, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 18, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Oct 8, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 8, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 8, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 8, 2024Administrative

Development fee collection

Building Inspection · DFCU

Oct 31, 2024Administrative

Zoning review

Planning · CP-ZOC

Jan 2, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 4, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 4, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Nov 5, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Nov 4, 2024Approved

Central Permit Bureau

Building Inspection · CPB

In progressIn Progress

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Approved
Estimated cost
$65,178
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mark Elliott Bucciarelli

Baukunst

ArchitectC23159
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202404029151 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record