1300 Van Ness Av
San Francisco permit 202404029189 · Nob Hill
Basement level: new back of house spaces sewing event staff and performers to be installed in the annex space. new spaces include dressing rooms, group viewing rooms, and single occupant shower/restroom. work includes multi-stall public restrooms and upgrades to (e) single user restrooms. (e) lift @
- Filed
- May 16, 2024
- Issued
- Aug 12, 2024 (3 months after filing)
- Completed
- Jul 3, 2025 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 38 stops across 6 departments
- Comments issued
- 9 times, by Building Inspection, Fire Department, Planning, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Apr 2, 2024 | Apr 2, 2024 | Approved |
Code enforcement Building Inspection · CES | Apr 2, 2024 | Apr 2, 2024 | Approved |
Intake Building Inspection · INTAKE | Apr 2, 2024 | Apr 2, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 4, 2024 | Apr 4, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 11, 2024 | Apr 11, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 12, 2024 | Apr 12, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Apr 12, 2024 | Apr 12, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 16, 2024 | Apr 16, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 17, 2024 | Apr 17, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 19, 2024 | Apr 19, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 22, 2024 | Apr 22, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 25, 2024 | Apr 25, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Apr 26, 2024 | May 7, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 30, 2024 | Apr 30, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | May 1, 2024 | May 1, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | May 3, 2024 | May 3, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 8, 2024 | May 16, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 16, 2024 | Jun 13, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 16, 2024 | May 22, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 16, 2024 | May 20, 2024 | Approved |
Public health review Public Health · HEALTH | May 16, 2024 | May 17, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | May 16, 2024 | Aug 9, 2024 | Administrative |
Public health food review Public Health · HEALTH-FD | Jun 6, 2024 | Jun 6, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 18, 2024 | Jul 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 26, 2024 | Jul 30, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 29, 2024 | Jul 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 30, 2024 | Jul 30, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jul 30, 2024 | Jul 30, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 31, 2024 | Jul 31, 2024 | Approved |
Public health food review Public Health · HEALTH-FD | Jul 31, 2024 | Jul 31, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 1, 2024 | Aug 1, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 1, 2024 | Aug 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 1, 2024 | Aug 1, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 1, 2024 | Aug 5, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 2, 2024 | Aug 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 5, 2024 | Aug 5, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2024 | Aug 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 9, 2024 | Aug 12, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,529,279
| Name | Role | License on permit |
|---|---|---|
| David Joel Masenten | Architect | C29921 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2025