600 20th St
San Francisco permit 202404049294 · Potrero Hill
Demolition of existing 9,200 sf commercial bldg, replacement bldg pa# 202110019676
- Filed
- Apr 4, 2024
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 11 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 3, 2024 | Apr 10, 2024 | Denied |
Building pre-screening Building Inspection · PRE-BLDG | Apr 8, 2024 | Apr 8, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 8, 2024 | Apr 8, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 8, 2024 | Apr 8, 2024 | Not Applicable |
Zoning review Planning · CP-ZOC | May 14, 2024 | May 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Demolitions
- Status
- Cancelled
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Michael Howard Pitler | Architect | C30445 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026