3355 Pacific Av
San Francisco permit 202404059401 · Presidio Heights
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa 202108236937. change media and gym rooms to new natatorium. expand scope of work to include new interior swimming pool, subterranean mechanical, electrical, and pool equipment vault beneath rear yard. no change to building exterior or conditioned area. add new fire sprinkler system th
- Filed
- Apr 22, 2024
- Issued
- Feb 25, 2025 (10 months after filing)
- Completed
- Not completed yet
- Review stops
- 25 stops across 4 departments
- Comments issued
- 9 times, by Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 4, 2024 | Apr 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 5, 2024 | Apr 23, 2024 | Administrative |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 8, 2024 | Apr 8, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Apr 9, 2024 | Apr 9, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 12, 2024 | Apr 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 23, 2024 | Jun 14, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 23, 2024 | May 22, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 23, 2024 | Apr 30, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 23, 2024 | Feb 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 14, 2024 | Sep 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 9, 2024 | Sep 19, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2024 | Sep 23, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 25, 2024 | Sep 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2024 | Oct 28, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2024 | Oct 21, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 16, 2024 | Oct 16, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 18, 2024 | Oct 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 19, 2024 | Dec 4, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 17, 2024 | Jan 22, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 24, 2025 | Jan 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 28, 2025 | Jan 28, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 28, 2025 | Feb 4, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2025 | Feb 12, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2025 | Feb 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 18, 2025 | Feb 25, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,550,000
| Name | Role | License on permit |
|---|---|---|
| Christopher A Roach Studio Vara Architecute | Architect | C30364 |
| Steven Paul Duquette T & S Structural | Engineer | S3019 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025