843 Montgomery St
San Francisco permit 202404119780 · Chinatown
Partition of finishes & fixtures. change of occupancy from m to b ab-017. ref de pa 2024-03188020. level 1 & mezzanine fire sprinkler referred
- Filed
- Apr 11, 2024
- Issued
- May 1, 2024 (within 1 month of filing)
- Completed
- Jun 5, 2024 (1 month after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 11, 2024 | Apr 11, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Apr 15, 2024 | Apr 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 15, 2024 | Apr 15, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 16, 2024 | Apr 16, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 16, 2024 | Apr 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 29, 2024 | Apr 29, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2024 | Apr 29, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 30, 2024 | Apr 30, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 30, 2024 | Apr 30, 2024 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Apr 30, 2024 | Apr 30, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 1, 2024 | May 1, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $24,000
| Name | Role | License on permit |
|---|---|---|
| Christopher A Roach Studio Vara Architecute | Architect | C30364 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022