CheckMyDesigner

3660 16th St

San Francisco permit 202404129892 · Castro/Upper Market

Home remodelFull plan reviewIssued
Street view · Sep 2026
Google Street View of 3660 16th St, Sep 2026
Scope of work
As written on the permit application.

G/f #3660: construct 2 new bath, renovate e bath. demo partition wall to add new bedroom. relocate water heater/range. demo stair that connects g/f to 3/f. 2nd fl #3662: construct new bath 2, renovate e bath,renovate e kitchen.

Timeline
Key dates from the city record.
Filed
Feb 12, 2025
Issued
Oct 14, 2026 (20 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
28 stops across 5 departments
Comments issued
10 times, by Planning, Building Inspection, Public Utilities
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Apr 12, 2024Administrative

Zoning review

Planning · CP-ZOC

Apr 12, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Apr 26, 2024Approved

Zoning review

Planning · CP-ZOC

Nov 1, 2024Issued Comments

Intake

Building Inspection · INTAKE

Nov 21, 2024Administrative

Zoning review

Planning · CP-ZOC

Nov 21, 2024Approved

Fire prevention review

Fire Department · SFFD

Nov 21, 2024Approved

Permit Center

Permit Center · PERMIT-CTR

Feb 7, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Feb 12, 2025Administrative

Structural plan approval

Building Inspection · PAD-STR

Mar 12, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Mar 7, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 28, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 4, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 14, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Nov 13, 2025Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Feb 28, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 14, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 28, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 20, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jun 13, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 17, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 24, 2025Approved

Building plan review

Building Inspection · BLDG

Sep 26, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Nov 3, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 17, 2025Approved

Zoning review

Planning · CP-ZOC

Nov 4, 2025Approved

Fire prevention review

Fire Department · SFFD

Nov 4, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 14, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$240,584
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Doug Lee

Doug Lee

ArchitectC74001
Kok Jin Yeo

Lcf Solutions

EngineerC83626
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202404129892 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record