555 07th St
San Francisco permit 202404160040 · South of Market
Modernization of a 3-stop single passenger elevator and elevator machine room with added ventilation to the machine room at 555 7th street in san francisco.
- Filed
- May 6, 2024
- Issued
- Feb 10, 2026 (21 months after filing)
- Completed
- Not completed yet
- Review stops
- 25 stops across 4 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 15, 2024 | Apr 22, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 16, 2024 | Apr 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 16, 2024 | May 6, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Apr 19, 2024 | Apr 19, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 19, 2024 | Apr 19, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Apr 23, 2024 | Apr 30, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 29, 2024 | Apr 29, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 29, 2024 | Apr 29, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 30, 2024 | Apr 30, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 6, 2024 | May 10, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | May 6, 2024 | May 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 6, 2024 | May 31, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | May 6, 2024 | May 14, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 6, 2024 | Oct 8, 2024 | Administrative |
Public Works disability access review Public Works · PW-DAC | May 24, 2024 | May 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 5, 2024 | Jul 5, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 5, 2024 | Jul 8, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 5, 2024 | Jul 9, 2024 | Approved |
Public Works disability access review Public Works · PW-DAC | Jul 5, 2024 | Aug 5, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 27, 2024 | Aug 27, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 9, 2024 | Sep 9, 2024 | Approved |
Public Works disability access review Public Works · PW-DAC | Sep 10, 2024 | Sep 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 10, 2024 | Sep 10, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 10, 2024 | Sep 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 8, 2024 | Feb 10, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $641,675
| Name | Role | License on permit |
|---|---|---|
| Eric S Robinson Paulett Taggart Architects | Architect | C28139 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025