3542 24th St
San Francisco permit 202404240674 · Mission
Flr 1: new fdn. convert 1,009 sf of garage/storage to habitable space for unit 1. add 1.5 baths, and add int stair. flr 2: unit 1 remodel kitchen, (2) baths, and laundry, connect flr 1 with int stair. flr 3: unit 2 relocate kitchen and bath. unit 1 (#3542)add bath, office, and int stair flr 2 to 3.
- Filed
- May 10, 2024
- Issued
- Aug 29, 2024 (4 months after filing)
- Completed
- Sep 1, 2026 (24 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 20 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 24, 2024 | Apr 24, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Apr 24, 2024 | Apr 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 24, 2024 | Apr 24, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | May 1, 2024 | May 7, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 2, 2024 | May 13, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | May 3, 2024 | May 3, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | May 6, 2024 | May 6, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | May 7, 2024 | May 7, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 13, 2024 | Jul 9, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 13, 2024 | Jun 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 13, 2024 | May 21, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2024 | May 17, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 13, 2024 | Aug 8, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2024 | Jun 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 30, 2024 | Jul 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 2, 2024 | Aug 2, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 5, 2024 | Aug 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2024 | Aug 7, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2024 | Aug 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 8, 2024 | Aug 29, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $817,500
| Name | Role | License on permit |
|---|---|---|
| Christi Ann Azevedo Azevedo Design | Architect | C31133 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025