224 Seacliff Av
San Francisco permit 202405021213 · Seacliff
Work to include foundation upgrade & upgrade structural framing. add new basement. remodel of 1st, 2nd & 3rd floors per drawings and to comply with bid_insp notice of violation 202547909 (12-12-2025) additional scope for removal of stucco on north,east and west side facades.
- Filed
- Dec 11, 2024
- Issued
- May 6, 2026 (17 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 48 stops across 6 departments
- Comments issued
- 11 times, by Permit Center, Building Inspection, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | May 2, 2024 | May 2, 2024 | Approved |
Code enforcement Building Inspection · CES | May 2, 2024 | May 2, 2024 | Approved |
Intake Building Inspection · INTAKE | May 2, 2024 | May 2, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 25, 2024 | Sep 25, 2024 | Approved-Stipulated |
Intake Building Inspection · INTAKE | Oct 10, 2024 | Oct 10, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 10, 2024 | Oct 10, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Oct 18, 2024 | Nov 4, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Oct 24, 2024 | Dec 12, 2024 | Administrative |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 25, 2024 | Oct 25, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Oct 29, 2024 | Oct 29, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 30, 2024 | Oct 30, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 18, 2024 | Dec 11, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 21, 2024 | Nov 21, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Dec 5, 2024 | Dec 5, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Dec 9, 2024 | Dec 9, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Dec 11, 2024 | Dec 11, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 12, 2024 | Dec 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 12, 2024 | Jan 30, 2025 | In Progress |
Mechanical and energy plan review Building Inspection · MECH | Dec 12, 2024 | Feb 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 12, 2024 | Dec 13, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2024 | Dec 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 12, 2024 | Jan 6, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 12, 2024 | May 1, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jan 23, 2025 | Jan 29, 2025 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Feb 4, 2025 | Feb 4, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 18, 2025 | Sep 3, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Apr 18, 2025 | May 7, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 8, 2025 | Nov 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 6, 2025 | Sep 3, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 6, 2025 | Aug 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 17, 2025 | Sep 17, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 19, 2025 | Sep 25, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 19, 2025 | Sep 25, 2025 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Sep 19, 2025 | Sep 19, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 19, 2025 | Sep 24, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 19, 2025 | Sep 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2025 | Sep 26, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 10, 2025 | Nov 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 25, 2025 | Apr 22, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 15, 2026 | Apr 15, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 15, 2026 | Apr 21, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 15, 2026 | Apr 16, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 15, 2026 | Apr 15, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2026 | Apr 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 15, 2026 | Apr 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 22, 2026 | Apr 27, 2026 | Approved |
Building inspector Building Inspection · BID-INSP | Apr 30, 2026 | May 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 1, 2026 | May 6, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,044,000
| Name | Role | License on permit |
|---|---|---|
| John F Dorr Doma Architects | Architect | C28936 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026