1096 Palou Av
San Francisco permit 202405031374 · Bayview Hunters Point
Other (type unconfirmed)Over-the-counter, with plansComplete
Scope of work
As written on the permit application.
Existing cmu trash enclosure to receive metal roof with steel column supports and metal infill panels.
Timeline
Key dates from the city record.
- Filed
- May 3, 2024
- Issued
- Oct 24, 2024 (6 months after filing)
- Completed
- Jul 15, 2025 (9 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
- Review stops
- 7 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | May 3, 2024 | May 3, 2024 | Approved |
Code enforcement Building Inspection · CES | May 3, 2024 | May 3, 2024 | Approved |
Intake Building Inspection · INTAKE | May 3, 2024 | May 3, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 8, 2024 | Oct 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2024 | Oct 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 16, 2024 | Oct 16, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Oct 24, 2024 | Oct 24, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
Permit details
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $10,000
People named on this permit
Only people we matched to a California license are listed.
| Name | Role | License on permit |
|---|---|---|
| Michelle Anne Sullivan Ssdp | Architect | C25093 |
| Stan Michael Wu Smw Associates | Engineer | S4665 |
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202405031374 on the city's permit tracking site
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025