724 A Masonic Av
San Francisco permit 202405031418 · Lone Mountain/USF
Repair fire damage throughout to comply with bid nov# 202316970. replace all finishes fixtures etc at 1 kitchen 2 bathrooms
- Filed
- May 3, 2024
- Issued
- Oct 3, 2024 (5 months after filing)
- Completed
- Oct 2, 2025 (12 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 10 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | May 3, 2024 | May 3, 2024 | Approved |
Apartment and hotel inspection Building Inspection · HIS | May 3, 2024 | May 3, 2024 | Approved |
Intake Building Inspection · INTAKE | May 3, 2024 | May 3, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2024 | May 7, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 22, 2024 | May 22, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Jun 12, 2024 | Jun 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2024 | Jun 12, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 12, 2024 | Jun 12, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jun 12, 2024 | Jun 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 3, 2024 | Oct 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| David W Kane Harrell Kane Struct Eng Inc | Engineer | S5278 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2016