350 Brannan St
San Francisco permit 202405071584 · Financial District/South Beach
2/f -demolition existing ceiling height partition, construction of new full height partitions, doors, millwork and finishes. associated power/lighting distribution, associated mechanical system distribution, associated life safety system changes and plumbing. structural scope of work encompasses
- Filed
- May 7, 2024
- Issued
- Apr 8, 2026 (23 months after filing)
- Completed
- Aug 6, 2026 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 16 stops across 3 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 7, 2024 | May 7, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 20, 2024 | May 20, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 21, 2024 | May 21, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 21, 2024 | May 21, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 11, 2024 | Jun 11, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 11, 2024 | Jun 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 24, 2024 | Jun 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 24, 2024 | Jun 24, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 9, 2024 | Jul 9, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 25, 2024 | Jul 25, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 25, 2026 | Mar 25, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 25, 2026 | Mar 25, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 25, 2026 | Mar 25, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2026 | Mar 25, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 2, 2026 | Apr 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 8, 2026 | Apr 8, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Douglas Wayne Mehl Fennie & Mehl Architect | Architect | C-17504 |
| Ryan Bogart | Engineer | 6104 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026