20 Eagle St
San Francisco permit 202405081663 · Castro/Upper Market
Interior remodel of extg single family home with attached garage at 20 eagle street. no change to extg height. no square footage added, no change to extg curb cut. reconfiguration of interior stair & lvl 2 bedroom, nw powder rm on lvl1. nw inset entry door. nw electric garage door,
- Filed
- May 8, 2024
- Issued
- Jan 31, 2025 (9 months after filing)
- Completed
- Jul 8, 2025 (5 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 15 stops across 5 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 8, 2024 | May 8, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 8, 2024 | May 8, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 9, 2024 | May 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 9, 2024 | May 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 9, 2024 | May 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 9, 2024 | May 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 24, 2025 | Jan 24, 2025 | Approved |
Intake Building Inspection · INTAKE | Jan 24, 2025 | Jan 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 24, 2025 | Jan 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 28, 2025 | Jan 28, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 28, 2025 | Jan 28, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 28, 2025 | Jan 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 29, 2025 | Jan 29, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 31, 2025 | Jan 31, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 31, 2025 | Jan 31, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Audrey A Bauer Studio Maven | Architect | C-36620 |
| Victor Ramos Ashley & Vance Engineering | Engineer | C86568 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026