1596 Post St
San Francisco permit 202405091826 · Japantown
2132 sf 3rd floor addition to existing 7125 sf 2story mixed use bldg including:3(n)beds,(2)new baths & (1)toilet,increasing bldg height from 27'3"to 38'-8.scope to create a 1048 sf garage w/(3)covered parking spaces,& 2nd fl remodeling(e)2375 sf(4)bedroom,(1)bath & (1)powder room.
- Filed
- Jun 24, 2024
- Issued
- Jul 15, 2025 (13 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 41 stops across 6 departments
- Comments issued
- 16 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 8, 2024 | May 23, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | May 9, 2024 | May 9, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | May 20, 2024 | May 20, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | May 22, 2024 | May 22, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jun 7, 2024 | Jun 14, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 11, 2024 | Jun 11, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 13, 2024 | Jun 13, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 14, 2024 | Jun 14, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 17, 2024 | Jun 25, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jun 25, 2024 | Jun 27, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 25, 2024 | Jul 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2024 | Jul 1, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 25, 2024 | Jun 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2024 | Jun 26, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 25, 2024 | Jul 10, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 25, 2024 | Jul 1, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Jun 26, 2024 | Sep 9, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 13, 2025 | Feb 25, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 13, 2025 | Feb 25, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Feb 13, 2025 | Mar 18, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2025 | Feb 19, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 13, 2025 | Feb 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 13, 2025 | Feb 25, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2025 | Feb 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 14, 2025 | Mar 25, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 14, 2025 | Mar 24, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 14, 2025 | Mar 19, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 14, 2025 | Mar 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 14, 2025 | Mar 18, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 14, 2025 | Mar 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 9, 2025 | May 19, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 9, 2025 | May 29, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | May 9, 2025 | Jun 4, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 9, 2025 | May 14, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | May 9, 2025 | May 12, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 9, 2025 | May 12, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 9, 2025 | May 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2025 | May 30, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 30, 2025 | Jul 1, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Jul 1, 2025 | Jul 1, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 1, 2025 | Jul 15, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,410,639
| Name | Role | License on permit |
|---|---|---|
| J Jarrell Conner Tierney Conner Design Studio | Architect | C28026 |
| Paul Chan Pctc Engineering | Engineer | 59840 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026