2331 Jackson St
San Francisco permit 202405142066 · Pacific Heights
122-sqft horizontal addition @ 2/f within (e) roof outline, lower driveway elevation by excavating 18-cu yards, ground flr bathroom remodel, replace (e) rear deck tile and guardrails, reaplce (e) rear juliet balcony, add new 30x36 roof hatch.
- Filed
- Jun 12, 2024
- Issued
- Feb 11, 2025 (8 months after filing)
- Completed
- Oct 30, 2026 (21 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 4 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 13, 2024 | May 24, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | May 14, 2024 | Jun 13, 2024 | Administrative |
Electrical pre-screening Building Inspection · PRE-MECH-E | May 17, 2024 | May 17, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | May 23, 2024 | May 23, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | May 24, 2024 | May 24, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | May 28, 2024 | Jun 10, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 6, 2024 | Jun 6, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 7, 2024 | Jun 7, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 7, 2024 | Jun 7, 2024 | Not Applicable |
Zoning review Planning · CP-ZOC | Jun 13, 2024 | Jun 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 13, 2024 | Aug 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 13, 2024 | Jul 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 13, 2024 | Jun 25, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 13, 2024 | Jun 20, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 13, 2024 | Jan 30, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Sep 5, 2024 | Sep 17, 2024 | Approved |
Zoning review Planning · CP-ZOC | Sep 5, 2024 | Sep 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 5, 2024 | Sep 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 5, 2024 | Sep 19, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 5, 2024 | Sep 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 23, 2025 | Jan 30, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 30, 2025 | Feb 11, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $415,000
| Name | Role | License on permit |
|---|---|---|
| Stephen Ross Walker Steve Walker Studio | Architect | C30281 |
| David W Kane Harrell Kane Struc Eng Inc. | Engineer | 5278 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026