121 Sagamore St
San Francisco permit 202405172332 · Oceanview/Merced/Ingleside
Convert portion of 1/f garage to new adu (567sf) habitable space -state adu, add 2-bedroom, bathroom & kitchen, install new mini-split heat pump & water heater, replace existing windows, install new insulation at exterior walls and ceiling.
- Filed
- Jul 12, 2024
- Issued
- Jan 26, 2026 (18 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 42 stops across 6 departments
- Comments issued
- 16 times, by Permit Center, Building Inspection, Planning, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 15, 2024 | May 29, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | May 17, 2024 | May 17, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | May 28, 2024 | May 28, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | May 29, 2024 | May 29, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 17, 2024 | Jul 10, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 19, 2024 | Jun 20, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 21, 2024 | Jun 21, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 27, 2024 | Jun 27, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Jul 11, 2024 | Jul 12, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 12, 2024 | Aug 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 12, 2024 | Jul 22, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2024 | Jul 24, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 12, 2024 | Jul 16, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 12, 2024 | Jul 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 12, 2024 | Jul 23, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 12, 2024 | Dec 30, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 29, 2024 | Oct 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2025 | Jan 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 13, 2025 | Feb 13, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 27, 2025 | Mar 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 28, 2025 | Apr 11, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 28, 2025 | Mar 28, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 28, 2025 | Apr 1, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 28, 2025 | Apr 3, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 28, 2025 | Apr 8, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 28, 2025 | May 1, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 2, 2025 | May 2, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 6, 2025 | Dec 2, 2025 | Not Applicable |
Zoning review Planning · CP-ZOC | Dec 5, 2025 | Dec 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 5, 2025 | Dec 8, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2025 | Dec 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 5, 2025 | Dec 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 5, 2025 | Dec 8, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 5, 2025 | Dec 11, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 23, 2025 | Dec 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 23, 2025 | Dec 26, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 23, 2025 | Dec 30, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 23, 2025 | Dec 23, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 23, 2025 | Dec 29, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 23, 2025 | Dec 23, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Dec 30, 2025 | Dec 30, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 30, 2025 | Jan 26, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $153,000
| Name | Role | License on permit |
|---|---|---|
| Maxwell Anthony Beaumont Beaumont & Associates | Architect | 24621 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2026