501 02nd St
San Francisco permit 202405202435 · Financial District/South Beach
6th fl/ ste 615. t.i. n) partitions, millwork, glazing, finishes, power/lighting/mech distribution. all non-structural.
- Filed
- May 20, 2024
- Issued
- May 31, 2024 (within 1 month of filing)
- Completed
- Nov 18, 2024 (6 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 7 stops across 3 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 20, 2024 | May 20, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 20, 2024 | May 20, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 20, 2024 | May 20, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 20, 2024 | May 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 20, 2024 | May 20, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 24, 2024 | May 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 31, 2024 | May 31, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $465,760
| Name | Role | License on permit |
|---|---|---|
| Douglas Wayne Mehl Fennie + Mehl Architects | Architect | C17504 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026