1340 Clay St
San Francisco permit 202405232867 · Nob Hill
Improvements in lobby including (n) finishes, light fixtures, an entry stair, relocated security station, mail area, accessible toilet.
- Filed
- May 23, 2024
- Issued
- Jul 10, 2026 (26 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | May 23, 2024 | May 23, 2024 | Approved |
Intake Building Inspection · INTAKE | May 23, 2024 | May 23, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 24, 2024 | May 24, 2024 | Administrative |
Intake Building Inspection · INTAKE | Jun 3, 2024 | Jun 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 3, 2024 | Jun 3, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 10, 2024 | Jun 10, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 11, 2024 | Jun 11, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 11, 2024 | Jun 11, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2024 | Jun 11, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 13, 2024 | Jun 13, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 10, 2026 | Jul 10, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $175,000
| Name | Role | License on permit |
|---|---|---|
| David Andrew Ramer Dra | Architect | C24056 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025