4030 21st St
San Francisco permit 202405242966 · Castro/Upper Market
Remodeling an (e) split-level home to enclose an (e) property line lightwell and adding a bathroom, adding skylights, remodeling (e) kitchen and bath; replacing some (e) doors and windows, revising closets and handrail.
- Filed
- Aug 19, 2024
- Issued
- Dec 24, 2024 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 24, 2024 | May 24, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 24, 2024 | May 24, 2024 | Approved |
Intake Building Inspection · INTAKE | Jun 12, 2024 | Jun 12, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 12, 2024 | Jun 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 12, 2024 | Jun 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2024 | Jun 12, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 12, 2024 | Jun 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 12, 2024 | Jun 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 31, 2024 | Jul 31, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jul 31, 2024 | Aug 16, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 5, 2024 | Aug 5, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 7, 2024 | Aug 7, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Aug 9, 2024 | Aug 9, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Aug 14, 2024 | Aug 14, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Aug 15, 2024 | Aug 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 19, 2024 | Aug 19, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 19, 2024 | Oct 25, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 19, 2024 | Dec 19, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 21, 2024 | Nov 21, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 27, 2024 | Nov 27, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 27, 2024 | Dec 17, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 27, 2024 | Nov 27, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 27, 2024 | Dec 4, 2024 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Nov 27, 2024 | Dec 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2024 | Dec 24, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Michael H Mullin Michael Mullin Architect | Payor | C25447 |
| Marcus Yan Design Everest Consulting | Engineer | C83553 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025