Scope of work
As written on the permit application.

Conversion of (e) storage space to accessory dwelling unit (adu) under state adu program including 1 bedroom, 1 bathroom, living room, kitchen/dining room, & laundry room. new openings for new windows. new electrical, lighting, & plumbing including new hot water heater, mech, & electrical meter.

Timeline
Key dates from the city record.
Filed
Jun 13, 2024
Issued
Aug 19, 2024 (2 months after filing)
Completed
Dec 20, 2024 (4 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
25 stops across 6 departments
Comments issued
5 times, by Planning, Building Inspection
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jun 6, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

May 29, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Jun 4, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jun 4, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jun 13, 2024Administrative

Zoning review

Planning · CP-ZOC

Jul 17, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jul 11, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 26, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Jun 13, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 24, 2024Approved

Urban forestry

Public Works · DPW-BUF

Aug 15, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Jun 26, 2024Approved

Permit Processing Center

Building Inspection · PPC

Aug 15, 2024Administrative

Structural plan approval

Building Inspection · PAD-STR

Jul 1, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jul 26, 2024Approved

Zoning review

Planning · CP-ZOC

Aug 1, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 1, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 6, 2024Approved

Zoning review

Planning · CP-ZOC

Aug 5, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 31, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 31, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 31, 2024Approved

Zoning review

Planning · CP-ZOC

Aug 5, 2024Approved

Development fee collection

Building Inspection · DFCU

Aug 6, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Aug 19, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$157,582
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Maurice Lombardo

Taylor Lombard Architects

ArchitectC-26362
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202405242976 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record