725 Sanchez St
San Francisco permit 202405293153 · Castro/Upper Market
To erect a 3-story over 1 basement, type v-b, single family residence. within delores heights special use district restrictions
- Filed
- Jul 3, 2024
- Issued
- Dec 9, 2025 (17 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 53 stops across 6 departments
- Comments issued
- 16 times, by Permit Center, Building Inspection, Fire Department, Public Utilities, Public Works, Planning
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 28, 2024 | Jun 12, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jun 7, 2024 | Jun 7, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 7, 2024 | Jun 7, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 7, 2024 | Jun 7, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Jun 23, 2024 | Jul 2, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 2, 2024 | Jul 15, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 15, 2024 | Jul 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 15, 2024 | Aug 16, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 15, 2024 | Aug 15, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 15, 2024 | Jul 18, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 15, 2024 | Jul 18, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jul 15, 2024 | Aug 1, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 15, 2024 | Aug 19, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Dec 20, 2024 | Dec 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 2, 2025 | Jan 2, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 18, 2025 | Mar 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 18, 2025 | Feb 18, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 18, 2025 | Feb 25, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 25, 2025 | Feb 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 4, 2025 | Mar 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 14, 2025 | Mar 14, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 17, 2025 | Apr 8, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 17, 2025 | Mar 18, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 17, 2025 | Mar 19, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Apr 8, 2025 | Apr 17, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | May 7, 2025 | Jun 6, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 4, 2025 | Aug 4, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Aug 19, 2025 | Oct 14, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 14, 2025 | Dec 9, 2025 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 14, 2026 | Apr 22, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 24, 2026 | May 6, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 29, 2026 | May 14, 2026 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | May 8, 2026 | May 8, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 8, 2026 | May 18, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 8, 2026 | Jun 15, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 8, 2026 | Jun 23, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | May 8, 2026 | May 22, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 8, 2026 | May 12, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 8, 2026 | May 14, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | May 8, 2026 | Jun 17, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 8, 2026 | May 20, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 8, 2026 | In progress | — |
Zoning review Planning · CP-ZOC | May 18, 2026 | May 18, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 8, 2026 | Oct 8, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 13, 2026 | Oct 21, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 15, 2026 | Oct 27, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 26, 2026 | Oct 26, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $1,491,030
| Name | Role | License on permit |
|---|---|---|
| Luat T Duong Ltd Architecture | Architect | C36383 |
| Jason Allen Pisano Hom-Pisano Engineering Inc | Engineer | C69708 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023