554 Commercial St #0
San Francisco permit 202405293155 · Chinatown
No exterior work planning approval under record # 2024001942 pta. full seismic retrofit, interior work includes ground floor bookstore, office, restrooms, new elevator, stairs at rear of interior.
- Filed
- Apr 23, 2025
- Issued
- Sep 29, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 40 stops across 6 departments
- Comments issued
- 12 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 29, 2024 | May 29, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 29, 2024 | May 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 29, 2024 | Jun 9, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jun 6, 2024 | Jun 13, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jun 9, 2024 | Jun 9, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 12, 2024 | Jun 12, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 13, 2024 | Jun 13, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 7, 2024 | Aug 21, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 15, 2024 | Aug 15, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 19, 2024 | Aug 19, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Aug 27, 2024 | Aug 27, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 25, 2024 | Dec 13, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 8, 2025 | Apr 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2025 | Apr 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 24, 2025 | Apr 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 24, 2025 | Jun 16, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 24, 2025 | Jun 4, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 24, 2025 | May 22, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 24, 2025 | Apr 29, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2025 | May 7, 2025 | Issued Comments |
Public Health HEALTH-MH | Apr 24, 2025 | Apr 25, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 24, 2025 | Sep 16, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Apr 25, 2025 | May 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 13, 2025 | May 19, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 21, 2025 | Jul 21, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 28, 2025 | Jul 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 29, 2025 | Jul 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 29, 2025 | Sep 8, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 29, 2025 | Aug 15, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 29, 2025 | Jul 31, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 29, 2025 | Aug 1, 2025 | Approved |
Public Health HEALTH-MH | Jul 29, 2025 | Aug 4, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 4, 2025 | Sep 4, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 8, 2025 | Sep 15, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2025 | Sep 9, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 8, 2025 | Sep 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 8, 2025 | Sep 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2025 | Sep 10, 2025 | Approved |
Public Health HEALTH-MH | Sep 8, 2025 | Sep 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 16, 2025 | Sep 29, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,718,000
| Name | Role | License on permit |
|---|---|---|
| Dean A Orr | Architect | C33650 |
| Leo Panian | Engineer | S4526 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026