678 28th St
San Francisco permit 202405293189 · Noe Valley
100% foundation replacement. remodel of (e) lower level and infill under deck to add 24sf of living space w/ 2(n) bedrooms and 2 (n) baths. dormer (e) attic to add berdroom and bathroom. add laundry room behind garage wall. reconfigure main level kitchen
- Filed
- Jul 18, 2024
- Issued
- Mar 19, 2025 (8 months after filing)
- Completed
- Dec 2, 2025 (8 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 36 stops across 6 departments
- Comments issued
- 8 times, by Planning, Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 29, 2024 | May 29, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 29, 2024 | May 29, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | Jun 6, 2024 | Jun 6, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jun 6, 2024 | Jun 6, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jun 17, 2024 | Jun 28, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jun 18, 2024 | Jun 18, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 21, 2024 | Jun 21, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 24, 2024 | Jun 24, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Jul 3, 2024 | Jul 16, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 12, 2024 | Jul 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 17, 2024 | Jul 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 18, 2024 | Sep 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 18, 2024 | Aug 13, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 18, 2024 | Aug 6, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 18, 2024 | Aug 22, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 18, 2024 | Jul 22, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 18, 2024 | Aug 2, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 18, 2024 | Nov 21, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 9, 2024 | Sep 24, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2024 | Sep 17, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 9, 2024 | Oct 2, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 9, 2024 | Sep 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 9, 2024 | Sep 13, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 13, 2024 | Sep 13, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 17, 2024 | Sep 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 17, 2024 | Sep 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 20, 2024 | Oct 9, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 20, 2024 | Sep 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 20, 2024 | Sep 25, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 25, 2024 | Nov 18, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 25, 2024 | Oct 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 25, 2024 | Nov 21, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 25, 2024 | Oct 28, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 25, 2024 | Oct 28, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 25, 2024 | Oct 29, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 26, 2024 | Mar 19, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $503,776
| Name | Role | License on permit |
|---|---|---|
| Steven Arthur Kellond Kellond Architects | Architect | C29787 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022