804 Steiner St
San Francisco permit 202405303272 · Hayes Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Altered site to pa# 201109144615, to introduce following changes: removal of level 0 to remove podium sub-basement level; reconfiguration/expansion of lvl 1 to provide parking for the 3-units on the property and include residential areas associated with unit 1 (which occupies lvl 1 and lvl 2)in
- Filed
- May 30, 2024
- Issued
- Feb 21, 2025 (9 months after filing)
- Completed
- Not completed yet
- Review stops
- 35 stops across 6 departments
- Comments issued
- 11 times, by Permit Center, Building Inspection, Fire Department, Public Utilities
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 29, 2024 | Jun 13, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jun 4, 2024 | Jun 4, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 7, 2024 | Jun 7, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 10, 2024 | Jun 10, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Jun 13, 2024 | Jul 3, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jul 3, 2024 | Jul 3, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 3, 2024 | Jul 3, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 3, 2024 | Jul 3, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Jul 3, 2024 | Jul 23, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 23, 2024 | Jul 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 23, 2024 | Aug 16, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 23, 2024 | Jul 25, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 23, 2024 | Jul 24, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jul 23, 2024 | Jul 25, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 23, 2024 | Dec 30, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Jul 24, 2024 | Sep 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 3, 2024 | Sep 19, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 4, 2024 | Sep 4, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 20, 2024 | Sep 24, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 20, 2024 | Oct 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 20, 2024 | Sep 23, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 30, 2024 | Sep 30, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 1, 2024 | Oct 1, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 3, 2024 | Oct 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 7, 2024 | Oct 9, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 7, 2024 | Oct 17, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Oct 7, 2024 | Oct 10, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 25, 2024 | Oct 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 28, 2024 | Oct 28, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Oct 29, 2024 | Oct 29, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 29, 2024 | Feb 21, 2025 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Dec 30, 2024 | Dec 30, 2024 | Approved |
Addendum 1: S-1
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 10, 2025 | Apr 29, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $271,000
| Name | Role | License on permit |
|---|---|---|
| Zachary Joseph Maddry Dmarc Studio | Architect | C30718 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026