201 03rd St
San Francisco permit 202406144533 · Financial District/South Beach
Prop h: new remodel of (e) restaruant on the ground fl. demo of walls, doors, ceilings,interior/exterior.finishes,fixtures,casework,storfronts,(e)signage,mep systems,(n)interior front of fixures,bar,storefront,bar/grill equipment & exterior finishes.
- Filed
- Jun 27, 2024
- Issued
- Oct 8, 2025 (15 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 50 stops across 7 departments
- Comments issued
- 14 times, by Public Health, Building Inspection, Public Works, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 13, 2024 | Jun 25, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 16, 2024 | Jun 16, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 20, 2024 | Jun 20, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 21, 2024 | Jun 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 27, 2024 | Jun 28, 2024 | Administrative |
Public health review Public Health · HEALTH | Jun 28, 2024 | Jun 28, 2024 | Administrative |
Public health food review Public Health · HEALTH-FD | Jun 28, 2024 | Jul 10, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jun 28, 2024 | Mar 4, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 1, 2024 | Jul 1, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2024 | Jul 1, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2024 | Jul 1, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 2, 2024 | Jul 2, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 8, 2024 | Jul 9, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 8, 2024 | Jul 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 11, 2024 | Jul 18, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 18, 2024 | Oct 1, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 20, 2024 | Sep 25, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 20, 2024 | Sep 20, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 20, 2024 | Sep 23, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 20, 2024 | Sep 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 23, 2024 | Sep 23, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 24, 2024 | Sep 24, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 29, 2024 | Oct 29, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 29, 2024 | Oct 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 31, 2024 | Oct 31, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 31, 2024 | Nov 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 31, 2024 | Nov 1, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 31, 2024 | Oct 31, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 1, 2024 | Nov 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 1, 2024 | Nov 1, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 4, 2024 | Nov 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 4, 2024 | Dec 4, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 4, 2024 | Dec 4, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 4, 2024 | Dec 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2024 | Dec 4, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 5, 2024 | Dec 5, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 5, 2024 | Dec 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 5, 2024 | Dec 5, 2024 | Approved-Stipulated |
Public health food review Public Health · HEALTH-FD | Dec 6, 2024 | Dec 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 9, 2024 | Dec 9, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 12, 2025 | Feb 12, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 12, 2025 | Feb 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 12, 2025 | Feb 13, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 13, 2025 | Feb 13, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 13, 2025 | Feb 13, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2025 | Feb 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2025 | Feb 13, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 18, 2025 | Feb 18, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | Feb 21, 2025 | Feb 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 4, 2025 | Oct 8, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $1,563,912
| Name | Role | License on permit |
|---|---|---|
| Geoffrey Buenavista Lim Innovation & Design In Arch | Architect | C-33396 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026