As written on the permit application.

To abate nov 202419488- change of use for first floor (e) retail space to fitness gym to include: alteration of (e) hardware, addition of (4) skylights, add exit passageway, replace (e) entry doors w/(n) accessible door. alteration to (e) men's restroom to accessible restroom. mep deffered.

Timeline
Key dates from the city record.
Filed
Aug 20, 2024
Issued
Nov 1, 2024 (2 months after filing)
Completed
Feb 19, 2026 (16 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
28 stops across 7 departments
Comments issued
8 times, by Building Inspection, Fire Department, Permit Center, Public Works
Review stopFinishedResult

Code enforcement

Building Inspection · CES

Jun 21, 2024Approved

Intake

Building Inspection · INTAKE

Jun 21, 2024Administrative

Zoning review

Planning · CP-ZOC

Jun 21, 2024Approved

Building plan review

Building Inspection · BLDG

Jul 5, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 5, 2024Approved

Building plan review

Building Inspection · BLDG

Jul 12, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 12, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jul 25, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Jul 23, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jul 23, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Aug 8, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Aug 8, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Aug 20, 2024Administrative

Building plan review

Building Inspection · BLDG

Aug 30, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 11, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 23, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Sep 11, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Sep 11, 2024Issued Comments

Public health review

Public Health · HEALTH

Aug 22, 2024Not Applicable

Permit Processing Center

Building Inspection · PPC

Oct 24, 2024Administrative

Structural plan approval

Building Inspection · PAD-STR

Sep 27, 2024Approved

Building plan review

Building Inspection · BLDG

Sep 23, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 2, 2024Approved

Fire prevention review

Fire Department · SFFD

Sep 20, 2024Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Oct 24, 2024Approved

Zoning review

Planning · CP-ZOC

Sep 23, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 23, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Nov 1, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$102,500
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Kevin Ka-Kiu Ma

Kevin Ma Architecture

ArchitectC29781
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202406215035 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record