1339 23rd Av
San Francisco permit 202406255249 · Sunset/Parkside
New accessory dwelling unit on 1st floor per state program ordinance no. 95-17. remove internal stairs between 1st & 2nd floor.
- Filed
- Jul 27, 2024
- Issued
- Oct 1, 2024 (2 months after filing)
- Completed
- Feb 10, 2025 (4 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 33 stops across 6 departments
- Comments issued
- 7 times, by Permit Center, Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 25, 2024 | Jul 3, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jun 26, 2024 | Jun 26, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 1, 2024 | Jul 1, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 3, 2024 | Jul 3, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jul 15, 2024 | Jul 19, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jul 25, 2024 | Jul 25, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 26, 2024 | Jul 29, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 29, 2024 | Aug 8, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 29, 2024 | Aug 6, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 29, 2024 | Aug 6, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 29, 2024 | Aug 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 29, 2024 | Jul 29, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 29, 2024 | Jul 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 29, 2024 | Jul 29, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 29, 2024 | Sep 24, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 27, 2024 | Sep 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 27, 2024 | Aug 27, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 27, 2024 | Aug 28, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Aug 27, 2024 | Aug 28, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 27, 2024 | Sep 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 27, 2024 | Sep 4, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 28, 2024 | Aug 28, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 11, 2024 | Sep 11, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 11, 2024 | Sep 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 11, 2024 | Sep 12, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 11, 2024 | Sep 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 11, 2024 | Sep 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 11, 2024 | Sep 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 12, 2024 | Sep 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 13, 2024 | Sep 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | Sep 16, 2024 | Sep 16, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | Sep 24, 2024 | Sep 24, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 24, 2024 | Oct 1, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $40,000
| Name | Role | License on permit |
|---|---|---|
| Stacy Chien-Yu Lin | Architect | C30812 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2021