CheckMyDesigner

3213 Folsom St

San Francisco permit 202406265325 · Bernal Heights

ADUFull plan reviewComplete
Street view · Dec 2024
Google Street View of 3213 Folsom St, Dec 2024
Scope of work
As written on the permit application.

Abate dcp 2023-007701enf. add one new adu in existing detached structure per govt code section 65852.2

Timeline
Key dates from the city record.
Filed
Sep 4, 2024
Issued
Apr 3, 2025 (7 months after filing)
Completed
Mar 13, 2026 (11 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
32 stops across 6 departments
Comments issued
10 times, by Permit Center, Building Inspection, Planning, Fire Department
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jul 16, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Jun 27, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Jul 3, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Jul 12, 2024Not Applicable

Permit Center

Permit Center · PERMIT-CTR

Sep 3, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Aug 27, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Sep 3, 2024Approved

Building inspector

Building Inspection · BID-INSP

Oct 21, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Sep 4, 2024Administrative

Zoning review

Planning · CP-ZOC

Sep 23, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Oct 2, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Sep 24, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 12, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 10, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 9, 2024Approved

Permit Processing Center

Building Inspection · PPC

Mar 26, 2025Administrative

Mechanical plan review quality control

Building Inspection · MECH-QC

Sep 12, 2024Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Dec 13, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Dec 17, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 19, 2024Approved

Zoning review

Planning · CP-ZOC

Dec 23, 2024Approved

Building plan review

Building Inspection · BLDG

Jan 31, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 12, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jan 30, 2025Approved

Building plan review

Building Inspection · BLDG

Feb 5, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Feb 27, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 27, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 28, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 28, 2025Approved

Zoning review

Planning · CP-ZOC

Mar 11, 2025Approved

Fire prevention review

Fire Department · SFFD

Mar 25, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Apr 3, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$124,675
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
David Edward Cumby

Cumby Architecture

ArchitectC-29182
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202406265325 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record