3213 Folsom St
San Francisco permit 202406265325 · Bernal Heights
Abate dcp 2023-007701enf. add one new adu in existing detached structure per govt code section 65852.2
- Filed
- Sep 4, 2024
- Issued
- Apr 3, 2025 (7 months after filing)
- Completed
- Mar 13, 2026 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 32 stops across 6 departments
- Comments issued
- 10 times, by Permit Center, Building Inspection, Planning, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 25, 2024 | Jul 16, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jun 27, 2024 | Jun 27, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 3, 2024 | Jul 3, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 12, 2024 | Jul 12, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Aug 20, 2024 | Sep 3, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 27, 2024 | Aug 27, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 3, 2024 | Sep 3, 2024 | Approved |
Building inspector Building Inspection · BID-INSP | Sep 4, 2024 | Oct 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2024 | Sep 4, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 4, 2024 | Sep 23, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 4, 2024 | Oct 2, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 4, 2024 | Sep 24, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 4, 2024 | Sep 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 4, 2024 | Sep 10, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2024 | Sep 9, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 4, 2024 | Mar 26, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Sep 12, 2024 | Sep 12, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Dec 13, 2024 | Dec 13, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 17, 2024 | Dec 17, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 19, 2024 | Dec 19, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 23, 2024 | Dec 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 29, 2025 | Jan 31, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 29, 2025 | Feb 12, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 29, 2025 | Jan 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 5, 2025 | Feb 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 27, 2025 | Feb 27, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 27, 2025 | Feb 27, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 28, 2025 | Feb 28, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 28, 2025 | Feb 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 11, 2025 | Mar 11, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 20, 2025 | Mar 25, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 26, 2025 | Apr 3, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $124,675
| Name | Role | License on permit |
|---|---|---|
| David Edward Cumby Cumby Architecture | Architect | C-29182 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024