233 Post St
San Francisco permit 202406275401 · Financial District/South Beach
Install (2) illuminated wall signs: "maxmara", (sign a) post street front facade, edge lit.
- Filed
- Jun 27, 2024
- Issued
- Aug 6, 2024 (1 month after filing)
- Completed
- Sep 25, 2024 (2 months after issuance)
- Review stops
- 13 stops across 4 departments
- Comments issued
- Once, by Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Jun 27, 2024 | Jun 27, 2024 | Administrative |
Intake Building Inspection · INTAKE | Jun 27, 2024 | Jun 27, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jun 27, 2024 | Jun 27, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 27, 2024 | Jun 27, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 27, 2024 | Jun 27, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 27, 2024 | Jun 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 2, 2024 | Aug 2, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 2, 2024 | Aug 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 2, 2024 | Aug 2, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 2, 2024 | Aug 2, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 2, 2024 | Aug 2, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 6, 2024 | Aug 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 6, 2024 | Aug 6, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Sign - erect
- Status
- Complete
- Estimated cost
- $3,000
| Name | Role | License on permit |
|---|---|---|
| Matthew Adam Reiskin Th3 Standard | Architect | C30220 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026