CheckMyDesigner

551 03rd St

San Francisco permit 202407015640 · Financial District/South Beach

Other (type unconfirmed)Full plan reviewComplete
Street view · Dec 2024
Google Street View of 551 03rd St, Dec 2024
Scope of work
As written on the permit application.

Remove / demolish: hydrogen equipment enclosure, hydrogen tanks, 2 hydrogen dispensers, associated equipment / piping. underground remote offload vault, & electrical switchgear / low voltage panel (remove conductor / cap conduits). remove piping trench & recompact. landscape & paving modifications.

Timeline
Key dates from the city record.
Filed
Oct 15, 2024
Issued
May 13, 2025 (7 months after filing)
Completed
Aug 22, 2025 (3 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 4 departments
Comments issued
10 times, by Permit Center, Building Inspection, Fire Department
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 16, 2024Administrative

Permit Center

Permit Center · PERMIT-CTR

Jul 12, 2024Issued Comments

Plumbing inspector

Building Inspection · PID-INSP

Jul 1, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Jul 7, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jul 9, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Jul 11, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Sep 17, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Sep 12, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Sep 13, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Sep 16, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Oct 15, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Oct 9, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Oct 10, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Oct 11, 2024Approved

Building plan review

Building Inspection · BLDG

Nov 15, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 19, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Oct 24, 2024Approved

Permit Processing Center

Building Inspection · PPC

Mar 27, 2025Administrative

Building plan review

Building Inspection · BLDG

Feb 12, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 25, 2025Approved

Fire prevention review

Fire Department · SFFD

Mar 10, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Mar 25, 2025Approved

Building plan review

Building Inspection · BLDG

Mar 24, 2025Approved

Central Permit Bureau

Building Inspection · CPB

May 13, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$400,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Patrick O'neill Fiedler

Fiedler Group

EngineerC38123
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202407015640 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record