551 03rd St
San Francisco permit 202407015640 · Financial District/South Beach
Remove / demolish: hydrogen equipment enclosure, hydrogen tanks, 2 hydrogen dispensers, associated equipment / piping. underground remote offload vault, & electrical switchgear / low voltage panel (remove conductor / cap conduits). remove piping trench & recompact. landscape & paving modifications.
- Filed
- Oct 15, 2024
- Issued
- May 13, 2025 (7 months after filing)
- Completed
- Aug 22, 2025 (3 months after issuance)
- Review stops
- 24 stops across 4 departments
- Comments issued
- 10 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 25, 2024 | Oct 16, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jun 27, 2024 | Jul 12, 2024 | Issued Comments |
Plumbing inspector Building Inspection · PID-INSP | Jul 1, 2024 | Jul 1, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jul 7, 2024 | Jul 7, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 9, 2024 | Jul 9, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 11, 2024 | Jul 11, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 5, 2024 | Sep 17, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 12, 2024 | Sep 12, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 13, 2024 | Sep 13, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 16, 2024 | Sep 16, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 30, 2024 | Oct 15, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 9, 2024 | Oct 9, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 10, 2024 | Oct 10, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 11, 2024 | Oct 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2024 | Nov 15, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 16, 2024 | Nov 19, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 16, 2024 | Oct 24, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 16, 2024 | Mar 27, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 12, 2025 | Feb 12, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 25, 2025 | Feb 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 10, 2025 | Mar 10, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 17, 2025 | Mar 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 24, 2025 | Mar 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 27, 2025 | May 13, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $400,000
| Name | Role | License on permit |
|---|---|---|
| Patrick O'neill Fiedler Fiedler Group | Engineer | C38123 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024