5400 Geary Bl
San Francisco permit 202407055849 · Outer Richmond
Reconstruct blade sign - electric, roof, double faced wall sign.
- Filed
- Dec 17, 2024
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 20 stops across 5 departments
- Comments issued
- 5 times, by Permit Center, Building Inspection, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 3, 2024 | Jul 15, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jul 12, 2024 | Jul 12, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 12, 2024 | Jul 12, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 12, 2024 | Jul 12, 2024 | Issued Comments |
Code enforcement Building Inspection · CES | Jul 15, 2024 | Jul 15, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jul 24, 2024 | Aug 2, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 31, 2024 | Jul 31, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 2, 2024 | Dec 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 18, 2024 | Jan 30, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 18, 2024 | Dec 23, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 18, 2024 | Dec 27, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 18, 2024 | Jan 13, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Dec 18, 2024 | Dec 27, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 18, 2024 | In progress | — |
Building Inspection MECH-E-QC | Dec 27, 2024 | Dec 27, 2024 | Administrative |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Sign - erect
- Status
- Filed
- Estimated cost
- $159,234
| Name | Role | License on permit |
|---|---|---|
| Irving Antonio Gonzales Gonzales Architects | Architect | C19332 |
| Diarmuid Hugo Mac Neill Dolmen Structural Engineer | Engineer | C56739 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026