1140 07th St
San Francisco permit 202407166537 · Mission Bay
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to bpa 201806283199 s3 interior updated spaces provided in level 2 of irwin and hooper pavilions, as well as levels 3-4 of hooper pavilion 1-hr fire separation added between levels 1 and 2 of hooper pavilion at group a occupancy. back check hours to be applied, dmj 07/23/2024;
- Filed
- Jul 24, 2024
- Issued
- Sep 9, 2025 (14 months after filing)
- Completed
- Jun 4, 2026 (9 months after issuance)
- Review stops
- 34 stops across 7 departments
- Comments issued
- 5 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 15, 2024 | Jul 24, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 22, 2024 | Jul 22, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 22, 2024 | Jul 22, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jul 23, 2024 | Jul 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 24, 2024 | Jul 25, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 25, 2024 | Jan 31, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 25, 2024 | Jul 31, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 25, 2024 | Aug 29, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2024 | Aug 22, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 25, 2024 | Aug 1, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 25, 2024 | Jan 13, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2024 | Jul 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2024 | Jul 29, 2024 | Approved |
Public health review Public Health · HEALTH | Jul 25, 2024 | Jul 29, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Jul 25, 2024 | Aug 1, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Aug 8, 2024 | Aug 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 29, 2024 | Sep 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 7, 2025 | Jan 7, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | Jan 8, 2025 | Jan 8, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2025 | Feb 10, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 14, 2025 | Jan 14, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 5, 2025 | Mar 5, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2025 | May 14, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 30, 2025 | May 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2025 | Jul 2, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 16, 2025 | May 16, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jun 7, 2025 | Jun 9, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 2, 2025 | Jul 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 2, 2025 | Jul 3, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 2, 2025 | Jul 9, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 2, 2025 | Jul 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 2, 2025 | Jul 24, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 2, 2025 | Jul 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 1, 2025 | Sep 9, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Jeanne K Gang Studio Gang Architects | Architect | C34329 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2018