1354 29th Av
San Francisco permit 202407176735 · Sunset/Parkside
Remodel/rearrange kitchen,bath,rooms.stairs,infill lightwell;add a full bath;add flat skylights.add 2 beds,2 baths,media on 1/f.add deck & doors at rear.replace wdws w/ alum wood-clad in-kind at front;wdws & doors at rear;garage dr,wh &furn;elec & plumb upgrades.replace roof.
- Filed
- Jul 17, 2024
- Issued
- Dec 23, 2024 (5 months after filing)
- Completed
- Feb 12, 2026 (14 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 9 stops across 4 departments
- Comments issued
- Once, by Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 17, 2024 | Jul 17, 2024 | Administrative |
Intake Building Inspection · INTAKE | Dec 5, 2024 | Dec 5, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 5, 2024 | Dec 5, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 12, 2024 | Dec 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 12, 2024 | Dec 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 12, 2024 | Dec 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 12, 2024 | Dec 12, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 12, 2024 | Dec 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 23, 2024 | Dec 23, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $180,000
| Name | Role | License on permit |
|---|---|---|
| Bill Leung Lau | Engineer | C54300 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023