517 Washington St
San Francisco permit 202407186772 · Chinatown
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revisions to pa 202407106168 & 202401304918 finishing the site with decompoosed granite & planting areas, and the construction of a support kiosk that includes electrical & plumbing infrastructure
- Filed
- Jul 18, 2024
- Issued
- Aug 8, 2024 (within 1 month of filing)
- Completed
- Jul 8, 2025 (11 months after issuance)
- Review stops
- 16 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 18, 2024 | Jul 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 18, 2024 | Jul 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 19, 2024 | Jul 19, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 19, 2024 | Jul 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 19, 2024 | Jul 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 19, 2024 | Jul 19, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 22, 2024 | Jul 22, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 25, 2024 | Jul 25, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 25, 2024 | Jul 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 5, 2024 | Aug 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 5, 2024 | Aug 5, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 7, 2024 | Aug 7, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 7, 2024 | Aug 7, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 7, 2024 | Aug 7, 2024 | Approved |
Public health review Public Health · HEALTH | Aug 8, 2024 | Aug 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 8, 2024 | Aug 8, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $423,000
| Name | Role | License on permit |
|---|---|---|
| Luma Jaffar | Architect | C-38314 |
| Laura Weyl | Engineer | S6376 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026