743 Green St #0
San Francisco permit 202407196947 · Chinatown
Pop up shed dormer @ rear of front bldg house, 30 sf add roof deck over new dormer and part of (e) flat roof,260 sf add railings. new interior access stairs to roof deck.remove 36sf of(e)skylights ,add 2 new windows, 22 s.f. net total 14 sf of new window. 433 sf new habitable space,no mep changes.
- Filed
- Jul 27, 2024
- Issued
- May 1, 2025 (9 months after filing)
- Completed
- Aug 1, 2025 (3 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 20 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 7, 2024 | Jul 24, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 19, 2024 | Jul 19, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Jul 22, 2024 | Jul 22, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 22, 2024 | Jul 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 26, 2024 | Jul 30, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 30, 2024 | Aug 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 30, 2024 | Aug 27, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 30, 2024 | Aug 27, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 30, 2024 | Apr 23, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2025 | Jan 14, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 22, 2025 | Jan 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 28, 2025 | Feb 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 28, 2025 | Jan 30, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 3, 2025 | Feb 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 5, 2025 | Feb 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 4, 2025 | Apr 15, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 4, 2025 | Apr 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 4, 2025 | Apr 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 21, 2025 | Apr 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 23, 2025 | May 1, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $90,000
| Name | Role | License on permit |
|---|---|---|
| Lisa Oi Wong Lisa Wong Architect | Architect | C17301 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023