200 Dolores St #5
San Francisco permit 202407237048 · Castro/Upper Market
Interior bathroom remodel. remove and replace portions of non bearing walls
- Filed
- Jul 23, 2024
- Issued
- Jul 30, 2024 (within 1 month of filing)
- Completed
- Jan 23, 2025 (6 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 7 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Jul 23, 2024 | Jul 23, 2024 | Approved |
Intake Building Inspection · INTAKE | Jul 23, 2024 | Jul 23, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 23, 2024 | Jul 23, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 23, 2024 | Jul 23, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 23, 2024 | Jul 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 23, 2024 | Jul 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 30, 2024 | Jul 30, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $37,897
| Name | Role | License on permit |
|---|---|---|
| Rex Stuart Mclean | Architect | C14477 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025