944 Capp St
San Francisco permit 202407247157 · Mission
Remodel (e) apartment uit including lower exist. slab. demo of (e) furnace and elimin. of all asbestos and (e) duct. install new mini split heat pump hvac system and elec wiring, new plumbing,insulation, kit cab,framing and furring as drawn. remove (e) chimney and non-load bearing walls.
- Filed
- Jul 24, 2024
- Issued
- Aug 14, 2024 (within 1 month of filing)
- Completed
- May 27, 2025 (9 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 9 stops across 5 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Jul 24, 2024 | Jul 24, 2024 | Approved |
Intake Building Inspection · INTAKE | Jul 24, 2024 | Jul 24, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 24, 2024 | Jul 24, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Jul 24, 2024 | Jul 24, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 24, 2024 | Jul 24, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 24, 2024 | Jul 24, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 24, 2024 | Jul 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 24, 2024 | Jul 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 14, 2024 | Aug 14, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $368,000
| Name | Role | License on permit |
|---|---|---|
| Ann Gloria Wimsatt | Architect | C39997 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026