67 B Mirabel Av
San Francisco permit 202407267339 · Bernal Heights
Conversion of (e)lower floors basement/ storage spaces of an existing 2-unit residence into a new adu(1011 sq.ft.)convert(e) 2 lower levels of storage/ basement areas into one(n)adu. add a new internal stairs connecting the 2 levels of the proposed adu.no cahange to existing 2 units @ 1st & 2nd fl
- Filed
- Mar 28, 2025
- Issued
- Feb 2, 2026 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 34 stops across 6 departments
- Comments issued
- 11 times, by Permit Center, Building Inspection, Planning, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 25, 2024 | Aug 6, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jul 29, 2024 | Jul 29, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 2, 2024 | Aug 2, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 5, 2024 | Aug 5, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Sep 4, 2024 | Sep 16, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 12, 2024 | Sep 12, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 13, 2025 | Mar 27, 2025 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Mar 20, 2025 | Mar 20, 2025 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Mar 25, 2025 | Mar 25, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 28, 2025 | Mar 31, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 31, 2025 | Apr 23, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 31, 2025 | Apr 23, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 31, 2025 | Apr 8, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 31, 2025 | Apr 2, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 31, 2025 | Apr 7, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 31, 2025 | Apr 16, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 31, 2025 | Apr 3, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 31, 2025 | Jan 27, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Dec 2, 2025 | Dec 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 2, 2025 | Jan 12, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 2, 2025 | Dec 9, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 2, 2025 | Dec 9, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 2, 2025 | Dec 3, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 2, 2025 | Dec 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 2, 2025 | Dec 11, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 12, 2026 | Jan 26, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 12, 2026 | Jan 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 12, 2026 | Jan 20, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 12, 2026 | Jan 14, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 12, 2026 | Jan 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 12, 2026 | Jan 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Jan 26, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jan 26, 2026 | Jan 27, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 27, 2026 | Feb 2, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $275,000
| Name | Role | License on permit |
|---|---|---|
| Yogesh Chitlangia Yogesh Chitlangia Architect | Payor | C31132 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023