593 Banks St

San Francisco permit 202407297450 · Bernal Heights

AdditionFull plan reviewComplete
Street view · Mar 2025
Google Street View of 593 Banks St, Mar 2025
Scope of work
As written on the permit application.

Retain (e) foundation & concrete slab & add (n) short cross wall foundation @ (n) garage door grade beam & 2 (n) shear wall. above (e) garage utility rm & middle bedrm add 2nd story include (n) stair to 2nd story, 2 bedrms,1 bath & 2 decks.covert gas to electrical: ev charger, cooktop,hp hvac.

Timeline
Key dates from the city record.
Filed
Aug 9, 2024
Issued
Nov 5, 2024 (3 months after filing)
Completed
Feb 12, 2026 (15 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 6 departments
Comments issued
5 times, by Building Inspection, Public Works, Public Utilities
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Aug 7, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Aug 9, 2024Administrative

Mechanical pre-screening

Building Inspection · PRE-MECH

Aug 2, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Aug 5, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Aug 5, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Aug 7, 2024Approved

Zoning review

Planning · CP-ZOC

Aug 9, 2024Approved

Building plan review

Building Inspection · BLDG

Sep 19, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 30, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 28, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 13, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Oct 30, 2024Administrative

Urban forestry

Public Works · DPW-BUF

Oct 16, 2024Not Applicable

Public Utilities Commission review

Public Utilities · SFPUC

Sep 4, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 15, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Oct 9, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 8, 2024Approved

Zoning review

Planning · CP-ZOC

Oct 7, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 15, 2024Approved

Zoning review

Planning · CP-ZOC

Oct 22, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 22, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 23, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Oct 24, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 22, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Nov 5, 2024Administrative

Fire prevention review

Fire Department · SFFD

Oct 29, 2024Approved

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$200,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Robert Michael Olexo

Olexo Design And Build

ArchitectC14091
David Owen Crestfield

Triangle Engineering

EngineerC050629
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202407297450 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record