7 Fallon Pl
San Francisco permit 202407307582 · Nob Hill
Removal of unauthorized work and to above 2020-001108enf. no changes proposed at exterior.
- Filed
- Dec 13, 2024
- Issued
- Mar 18, 2025 (3 months after filing)
- Completed
- Jul 23, 2025 (4 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 13 stops across 3 departments
- Comments issued
- 3 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 29, 2024 | Aug 21, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 6, 2024 | Aug 6, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Aug 8, 2024 | Aug 8, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Nov 1, 2024 | Nov 1, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 1, 2024 | Nov 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 13, 2024 | Dec 13, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 13, 2024 | Dec 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 13, 2024 | Dec 31, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 13, 2024 | Feb 12, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Dec 13, 2024 | Feb 12, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 6, 2025 | Jan 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 6, 2025 | Jan 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 12, 2025 | Mar 18, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $3,000
| Name | Role | License on permit |
|---|---|---|
| Dan William Phipps Dan Phipps Architects | Architect | C15366 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025