55 Music Concourse Dr
San Francisco permit 202407307608 · Golden Gate Park
Renovation of (e) cafe shop facility, removal of part of (e) ceilings. replace (e) equipment, relocation of (e) light fixtures and mechanical hvac.
- Filed
- Jul 30, 2024
- Issued
- Sep 20, 2024 (2 months after filing)
- Completed
- Jun 13, 2025 (9 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 17 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Jul 30, 2024 | Jul 30, 2024 | Approved |
Intake Building Inspection · INTAKE | Jul 30, 2024 | Jul 30, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 1, 2024 | Aug 1, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Aug 1, 2024 | Aug 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 1, 2024 | Aug 1, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 1, 2024 | Aug 1, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 1, 2024 | Aug 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 19, 2024 | Aug 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 19, 2024 | Aug 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 27, 2024 | Aug 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 28, 2024 | Aug 28, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 29, 2024 | Aug 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 30, 2024 | Aug 30, 2024 | Approved |
Public health review Public Health · HEALTH | Sep 11, 2024 | Sep 11, 2024 | Administrative |
Public health review Public Health · HEALTH | Sep 18, 2024 | Sep 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2024 | Sep 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 20, 2024 | Sep 20, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $939,566
| Name | Role | License on permit |
|---|---|---|
| Mark Robert Cavagnero | Architect | C19521 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2013