1145 Wisconsin St
San Francisco permit 202407317667 · Potrero Hill
Addition of (n), 2 (n) bathrooms & family room on 1st fl. relocate (e) bedroom & (e) bathroom & remodel (e) kitchen on 2nd fl. remodel (e) bedroom and addition of (n) bathroom at attic. (n) dormer on roof.
- Filed
- Oct 23, 2024
- Issued
- Jun 6, 2025 (7 months after filing)
- Completed
- Sep 9, 2025 (3 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 38 stops across 6 departments
- Comments issued
- 11 times, by Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 31, 2024 | Jul 31, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 31, 2024 | Jul 31, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 7, 2024 | Aug 7, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 16, 2024 | Oct 3, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 20, 2024 | Oct 23, 2024 | Administrative |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 23, 2024 | Sep 23, 2024 | Not Applicable |
Code enforcement Building Inspection · CES | Sep 24, 2024 | Sep 24, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 25, 2024 | Sep 25, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 30, 2024 | Sep 30, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Oct 3, 2024 | Oct 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 23, 2024 | Dec 24, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 23, 2024 | Nov 14, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 23, 2024 | Oct 31, 2024 | Not Applicable |
Fire prevention review Fire Department · SFFD | Oct 23, 2024 | Oct 25, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2024 | Oct 30, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 23, 2024 | Oct 24, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 23, 2024 | May 22, 2025 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Jan 10, 2025 | Jan 10, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 28, 2025 | Mar 5, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 28, 2025 | Mar 3, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 28, 2025 | Mar 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 28, 2025 | Mar 3, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 28, 2025 | Mar 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 20, 2025 | Mar 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 20, 2025 | Apr 1, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 20, 2025 | Mar 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 20, 2025 | Mar 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 20, 2025 | Mar 21, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 20, 2025 | Mar 26, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 29, 2025 | Apr 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 29, 2025 | May 5, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2025 | Apr 29, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 29, 2025 | Apr 30, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 29, 2025 | Apr 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 29, 2025 | May 2, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 15, 2025 | May 15, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 19, 2025 | May 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 22, 2025 | Jun 6, 2025 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $590,000
| Name | Role | License on permit |
|---|---|---|
| Sergio Mayorga | Architect | C40929 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025